Published: 1st Feb 2012
Countries: Iraq
Solutions: Bridges and Underground Structures, Civil Engineering, HDD, Large Diameter HDD
Our branch in Iraq was awarded a contract to supply and install 7 parallel pipelines of 48 Inch carbon steel pipes, 1,200 metres in length each, underneath Shatt Al Arab by HDD method.
The project also includes construction of concrete water reservoir, tie-in of pipelines to the inlet and outlet structures for the Siphon.
The foundation works are expected to be completed in 11 months and is located in Basrah City.