Client
Consultant
Main Contractor
Location
Start Date
Completion Date
Back filling including vibro compaction at existing basin: 300,000 m3
Formation of hydrolift basin constructed of diaphragm wall (800 m) and reinforced concrete walls
A piled reinforced concrete platform (550 piles),
approximately 130 m x 70 m, designed to support the
loads from vessels under repair and sections of new ships during launching
Construction of two berthing dolphins – 6 x 8.5 m depth each
Installation of two mooring piles
Foundation for removable steel landward gate (gate constructed by others)
Gate abutments and sill for floating seaward gate (gate constructed by others)