Safina Project, Dubai Drydocks

Safina Project, Dubai Drydocks

Ship Launch and Recovery Facility – Design & Construction

PORTS & SHIPPING • SHIP LIFT BASINS • SHEET PILES • COFFERDAM • DIAPHRAGM WALLS • ROTARY BORED PILES • VIBRO COMPACTION
Project Details

Back filling including vibro compaction at existing basin: 300,000 m3

Formation of hydrolift basin constructed of diaphragm wall (800 m) and reinforced concrete walls

A piled reinforced concrete platform (550 piles),
approximately 130 m x 70 m, designed to support the
loads from vessels under repair and sections of new ships during launching

Construction of two berthing dolphins – 6 x 8.5 m depth each

Installation of two mooring piles

Foundation for removable steel landward gate (gate constructed by others)

Gate abutments and sill for floating seaward gate (gate constructed by others)

View Project Data Sheet