Currently the deepest dig in Abu Dhabi and a very specialised project due to the excavation’s depth of 20 m, and close proximity of the sea and nearby buildings.
D-Wall Length : 465 LM
Shoring Depth : 24.5 m & 26.5 m
Excavation : 500,000 m³
Anchors : 722 nos.
Struts (two levels) : 1.0 & 1.2 m dia.
Number of Piles : 858 nos.
Reinforcement Steel : 4,372 tons
Concrete Volume : 20,376 LM
Total Length Drilled : 18,488 LM