Bahrain LNG Import Terminal Project

Horizontal Directional Drilling (HDD)

Installation of 2130 m of 24” gas pipeline which was welded and laid on the sea bed, and a parallel 225 mm HDPE duct for fibre optic cable (FOC).

Shore approach installation of 550 m 24” gas pipeline & 2 nos. of parallel 450 mm HDPE ducts for power cables.

Rig Type: 350 Ton Drilling Rig
Marine Equipment: Spud barges, multicats, tugs, speed boats and divers

View the Project Data Sheet:

Client

National Oil & Gas Authority (Nogaholding)

Consultant

COWI - Bahrain

Main Contractor

GS Engineering & Construction Corp.

HDD Contractor

NSCC International Limited

Location

Bahrain

 Industries

Energy

Tags

Bahrain, Pipeline Crossing, Oil & Gas, Large Diameter HDD, Energy